Connecting a flat or house to mains gas in Bulgaria: the steps, the documents, the neighbours' consent and the costs
Gas is one of the things buyers ask us about most often once they have chosen a property. Whether it is the right system for a particular home is covered separately in our comparison of heating systems. This guide follows the process itself, from checking whether there is a network to lighting the boiler for the first time.
Checked as of November 2026.
First: is there a network in your street?
Gas distribution networks are built by the company licensed for that area (Art. 98b(1) of the Spatial Development Act, ZUT). In Sofia and many other cities this is Overgas; other municipalities are served by other companies. Start by asking whether your street already has gas or is due to get it; Overgas answers this on its national line 0700 11 110 or at a customer centre.
If you are building a new house, the gas utility data is requested together with the design visa — see our guide to power, water and sewerage for a new house.
Step 1: the connection application
The procedure is set out in Ordinance No. 4 of 2013 on connection to gas transmission and distribution networks. The application (Art. 33) states:
- the applicant's name and personal ID number, the property address and a correspondence address;
- a description of the property, the gas appliances by type and number, and the date you want to start using gas.
Attached to it:
- proof of ownership (or of a right to build);
- for a block of flats — the minutes of the general assembly approving gasification and a notarised power of attorney for the elected representative;
- declarations allowing the company a right to build or an easement for its equipment, and access to maintain it.
Step 2: the reply and the contract
The distribution company studies the request and, within 20 working days, gives its consent or a reasoned refusal (Art. 34(2)). The reply sets the conditions, method and point of connection and a proposed deadline.
Next comes the connection contract (Art. 36). It must state the ownership boundary, the metering point, the deadlines for the service line and for your installation, and the connection price. Read the deadlines carefully: the ordinance sets no fixed number of days for the actual connection — it is whatever the contract says.
Who builds what
The split is clear, and it matters when you compare quotes:
| Part | Who builds and owns it |
|---|---|
| Street network | The distribution company, at its own cost (Art. 98b ZUT) |
| Service line to the building and the metering equipment | The company; they remain its property (Art. 24(2), Ordinance No. 4) |
| In-building and internal installation, appliances | The owner, at the owner's cost (Art. 98b(3) ZUT; Art. 38, Ordinance No. 4) |
Service lines are normally placed outside the customer's property (Art. 25). If the equipment has to sit in your garden, the company first obtains a right to build or an easement (Art. 37).
Step 3: design and installation — no building permit
Installing building gas installations in residential and holiday buildings does not require a building permit (Art. 151(1)(10) ZUT). That does not mean "no paperwork":
- the installation is designed by a licensed designer;
- the design is approved by a technical supervision body;
- it is installed by a firm qualified for gas work, and safe operation is governed by the ordinance under Art. 200(1) of the Energy Act;
- the appliances must not be connected while the installation is pressure-tested — the company will ask for the test records.
The connection to the network is made only under a contract with the utility (Art. 177(5) ZUT).
A flat in a block: the neighbours' consent
When the gas pipes run through common parts, a specific rule applies. A gas supply installation in a condominium building needs a general assembly decision passed by more than 50% of the ideal shares in the common parts, or the express written consent of half of the co-owners (Art. 186(2) ZUT). How the meeting is called and how the minutes are drawn up is explained in our guide to the general assembly of an apartment block.
In practice there are two layouts in a block:
- A shared boiler room for the building, with one gas meter and the costs split between flats.
- Individual supply — a common vertical riser in the stairwell with a separate meter for each flat, or meter cabinets on the facade or in the entrance with separate pipes to each home.
The gasification decision does not settle how the cost of the riser is shared. Record in the minutes who takes part and in what share, and on what terms a neighbour who declines now can join later. If the design affects the facade or a shared chimney, make sure the decision covers that too. Work inside the flat itself follows the general rules in our guide to renovating a flat in a block.
A house: a shorter route
A detached house needs no neighbours' consent. If the house is co-owned (heirs, relatives on different floors), Art. 186 ZUT requires the written consent of half of the co-owners. The questions we see more often with houses are technical: where the meter cabinet will go, whether the service line has to cross someone else's land, and whether there is a suitable place for the boiler and its flue.
What the bill is made of
We do not publish a single figure, because it depends on the company, the property and the appliances. The bill has several parts:
- Connection price — regulated by the energy regulator KEVR (Art. 30(1)(11) of the Energy Act), set per customer group for each company and paid when the contract is signed. Ask your company for it in writing.
- Design of the installation.
- Construction of the in-building and internal installation — in a block, also your share of the riser.
- Appliances — boiler, hot-water cylinder, hob, and the flue.
For items 2–4, get at least two written quotes with a specification. Compare the scope, not just the total.
Buying a home that already has gas
Ask for the connection contract, the installation design and the test records, plus the latest bill. Agree in the preliminary contract that the seller will cooperate in transferring the gas account.
In short
- Apply to the company licensed for your area; it must reply within 20 working days (Ordinance No. 4/2013).
- The service line and meter belong to the company; the in-building installation is at your cost.
- A gas installation in a home needs no building permit, but it does need a design and technical supervision.
- In a block you need a decision by more than 50% of the ideal shares (Art. 186(2) ZUT) — agree the cost split too.
- The connection price is regulated — ask for it in writing.
If you are considering gas for a house or flat you are buying or selling, call us or visit our office. We will help you check what has been built, which documents exist and how gas affects the value of the property.
Checked as of November 2026. This is general information and does not replace advice from a designer or the gas distribution company.