Sofia signs EUR 282 million EU grant: new metro trains, trolleybuses and e-buses, the metro through Slatina and to Obelya station
On 12 November Sofia Municipality signed a contract for EUR 282 million in EU grant funding for public transport and for streets and boulevards in the capital. The contract was signed by Mayor Vasil Terziev and the Minister of Regional Development and Public Works, Ivan Shishkov, the municipality announced.
The money comes from the Development of the Regions 2021–2027 programme, Priority 1 "Integrated urban development". According to the ISUN monitoring system, it is the largest contract by value under this programme with Sofia Municipality as beneficiary since the 2007–2013 period. For comparison, phase one of "Integrated Sofia Urban Transport" received about EUR 36.4 million and phase two about EUR 42.2 million.
What will be funded
A total of 141 new public transport vehicles, plus metro construction:
| Area | What the contract covers |
|---|---|
| Metro | extension of Line 3 through Slatina; a metro station at Obelya railway station with a tunnel link to the Obelya metro depot |
| Metro trains | 16 new trains for lines 1, 2 and 4 (8 of them under an additional agreement of 27 October), delivered by autumn 2028 |
| Trolleybuses | 75 low-floor trolleybuses with batteries for off-wire running — 40 articulated (18 m) and 35 single (12 m) |
| E-buses | 50 low-floor fast-charging electric buses — 35 at 12 m and 15 at 18 m, plus charging stations |
| Streets | the already completed Todor Kableshkov Blvd (between Louis Ayer St and Cherni Vrah Blvd) and Rozhen Blvd (from the railway overpass to the Northern Speed Tangent) |
Part of the money, the municipality says, will cover investments already made.
The new routes
With the new trolleybuses the municipality plans to:
- extend trolleybus line 3 to Mladost-4 with a link to Vrazhdebna;
- extend line 8 to Orlandovtsi;
- add new trolleybus links Lyulin – Gotse Delchev and Nadezhda – Mladost-1.
The e-buses will run two new ring lines — 71 between Levski G and Gotse Delchev and 75 between Geo Milev and Pavlovo, including along G. M. Dimitrov Blvd and Todor Kableshkov Blvd.
Together with the long-term loan the municipality will take out, the goal is for all surface public transport vehicles to be low-floor and air-conditioned by 2030.
EU grant and bank loan — two different things
This funding is a grant and is separate from the investment loan of up to EUR 183.5 million, for which UBB was ranked first at the end of October. The two sources complement each other — EU money for vehicles and the metro, the loan for road projects and further vehicles.
What it means for buyers, owners and tenants
From here on, this is our assessment rather than the municipality's.
A signed contract is a stronger argument than a promise. For the neighbourhoods along the new routes — Mladost-4, Vrazhdebna, Orlandovtsi, Nadezhda, Lyulin, Gotse Delchev, Pavlovo, Geo Milev — the funding is now secured, not just planned. When services actually start still depends on vehicle deliveries and on the infrastructure that has to be built.
Buyers. If you are considering a home in Slatina or near Obelya station, the metro is a real factor — see which neighbourhoods are getting new metro stations and what to check and how far the tunnel under Slatina has progressed. But don't pay a premium for a station that hasn't opened as if it were already running.
Owners and sellers. A new trolleybus or e-bus route is a good selling point, but only with specifics: the line number, the nearest stop, the expected start date.
Landlords and tenants. Better transport in outlying districts such as Mladost-4 or Orlandovtsi usually widens the pool of tenants willing to live there without a car. The effect comes when the line starts running, not when the contract is signed.
In brief
- Sofia signed a EUR 282 million EU grant contract under the Development of the Regions programme.
- 141 new vehicles: 16 metro trains, 75 trolleybuses, 50 e-buses.
- Metro through Slatina and a station at Obelya; new routes to Mladost-4, Vrazhdebna and Orlandovtsi.
- The grant is separate from the loan of up to EUR 183.5 million.
Buying or selling a property in a district along the new routes? Call us or visit the Scala Di office — we will check together what is planned around the specific address and how to factor it into the price.