Sofia's Slatina metro branch: the tunnel boring machine Vitosha reaches Sitnyakovo, with 80% of the tunnel built
On 29 September, Sofia Municipality announced that the tunnel boring machine Vitosha, which is digging the Slatina branch of Metro Line 3, has reached Sitnyakovo station. According to the metro company Metropolitan EAD, about 3.7 km of the tunnel is now built — roughly 80% of its length. Around 900 metres remain, which the municipality expects to complete by the end of 2026, as BTA also reported.
What has been built so far
- Construction of the section began at the end of 2023. The machine set off on 6 February 2024 from the launch shaft on Tsarigradsko Shose in Mladost, near St Anna hospital.
- Along the way it has passed through the pre-built structures of the future Trakia station and of the Arena Sofia, SK CSKA, Slatina and Geo Milev stations.
- Sitnyakovo — on the boulevard of the same name, at Geo Milev Street — is the last station on the 6 km section. From there the machine continues to the exit shaft in the grounds of the G. S. Rakovski Military Academy.
- The tunnel is double-track, with an outer diameter of 9.05 m. The machine weighs about 1,600 tonnes, is 86 m long and in normal operation advances 10–15 m a day. More than 22,000 concrete segments will be used along the full route.
- According to the municipality, a total of €58.4 million was earmarked for the section when Sofia's 2026 budget was debated.
The main challenge, the municipality says, is the large number of existing underground networks along the route — water mains, sewers, power cables — which require careful planning and monitoring.
One important caveat: a finished tunnel is not yet a working line. Track, systems and station fit-out follow the tunnelling. The 29 September announcements give no date for passenger service, so neither do we.
Which neighbourhoods it serves
The branch links Oborishte, the Slatina district (the Geo Milev and Hristo Smirnenski neighbourhoods) and Mladost at Tsarigradsko Shose. These are established residential areas where, for many residents, there is currently no metro station within walking distance. The project is part of the capital's wider transport investment drive, which we covered recently in our piece on Sofia's €367 million investment programme.
What it means for you
If you are buying: proximity to a future metro station is usually priced in by the market, but the premium builds gradually and some of it may already be in asking prices. Check the real walking distance to the station — along the streets, not as the crow flies — and where the entrances will be. Don't pay a premium for "the metro next year" until an opening date has been announced.
If you are viewing a home near a station or shaft: ask about noise and vibration during construction, temporary traffic arrangements and parking. Some disruption will continue after tunnelling while the stations are being finished.
If you are selling: progress on the metro is a genuine selling point — state the distance to the nearest future station in your listing. At the same time, Sofia buyers are more cautious than a year ago (see our H1 market report), so keep the price realistic.
If you let or rent: rental demand near metro stations tends to be more resilient. If you are buying to let, base your yield on today's rent and treat any uplift after the line opens as a bonus, not the foundation of the calculation.
In brief
- The TBM Vitosha has reached Sitnyakovo, the last station on the 6 km Slatina section.
- About 3.7 km (80%) of the tunnel is built; around 900 m remain to the exit shaft, expected by the end of 2026.
- The route serves Oborishte, Geo Milev, Hristo Smirnenski and Mladost at Tsarigradsko Shose.
- No date for passenger service has been announced — buy on today's facts, not on promises.
If you are thinking of buying or selling a home in Geo Milev, Slatina, Mladost or Oborishte and want to work out what the future metro really means for a specific property, give us a call or visit our office — we will go through it together.
Source: Sofia Municipality and BTA, 29 September 2026. This information is general and does not constitute legal or financial advice.