Landslide in Smolyan's Nevyastata district carries part of a street into a building excavation; building control halts construction until the slope is secured

Landslide in Smolyan's Nevyastata district carries part of a street into a building excavation; building control halts construction until the slope is secured

Construction of a residential building in Nevyastata, a district of the mountain town of Smolyan, has been halted after prolonged rain on 8 November sent earth, part of a car park and part of one carriageway of the street into the building's excavation. On 12 November Rumen Sakaliyski, head of the Regional Directorate for National Construction Control (RDNSK) in Smolyan, said an emergency order had been issued and the site will stay closed until the area is fully reinforced, the Bulgarian News Agency (BTA) reported.

What happened

The landslide happened on Sunday, 8 November. According to BTA, soil, part of a car park and part of one carriageway slid into the excavation. No one was injured.

Lachezar Tsvetkov, manager of the firm reinforcing the site, put it down to the large volume of rainwater after the long spell of rain – in his words, the street had been channelling water towards the site. He believes the rest of the street and the neighbouring residential buildings are not at risk. Deputy mayor Marian Tsekova said everyone involved in the construction must urgently take measures to shore up the slope. The municipality has opened an inspection.

What building control decided

Under the emergency order, only works to reinforce the excavation are allowed on site. The urgent measures include covering the affected section with plastic sheeting to keep more rain out of the soil, diverting water away from the street and building an additional embankment.

Two options are being considered for the retaining structure – anchoring into solid rock or adding supports. Only once the structural solution is approved and drainage is in place can work on the foundation slab continue.

Prof. Nikolay Zhechev, an expert in above- and below-ground construction who inspected the site for the municipality, concluded that surface water and groundwater had seeped into the fill, increased the pressure on the retaining structure and compromised it.

The dispute with the neighbours

Residents have opposed the development for more than ten years, and the plot has changed hands several times. An earlier case before the Smolyan Administrative Court was dismissed because the project was then only at the stage of an investment intention.

Neighbour Stefka Marinska alleges breaches of planning rules – she disputes the higher building density and says the permitted height was raised from 10 to 20 metres to the cornice. She questions the geological surveys, says there is groundwater in the area and that cracks have appeared next to one of the residential buildings. Residents have filed a new appeal against the building permit with the Smolyan Administrative Court and alerted other bodies, including RDNSK. These claims have yet to be examined.

What it means for buyers, neighbours and owners

The case echoes the landslide next to a building site in Varna's Asparuhovo district that we covered in October, when the regional development minister said that building breached planning law. The pattern is similar: water, an excavation on a slope and shoring that did not hold.

If you have bought, or are considering, an off-plan home in a project like this:

  • An emergency order stops everything except the reinforcement work. That almost certainly means delays. Check what your contract says about deadlines, penalties and force majeure.
  • Tie your payments to the construction stages (Acts 14, 15 and 16), not to calendar dates. If an instalment is due on a fixed date while the site is stopped, talk to a lawyer before you pay.
  • Ask the developer whether any appeals against the building permit are pending. We explained how to check the company itself in our guide to vetting the developer before an off-plan purchase.

If you live next to a building site on a slope:

  • Photograph and date any cracks in your building, fence and paving now – if new ones appear, you will have evidence of when they formed.
  • Report concerns to the municipality and RDNSK in writing. A written report leaves a record and obliges the authorities to respond.

If you are buying on steep ground:

  • Ask about the engineering-geological survey and how water is drained from the plot and from the street above it.
  • Check whether the area is in the landslide register. We walked through how to do it in our guide to checking natural hazards before you buy.

In brief

  • On 8 November, after days of rain, part of a street and car park in Smolyan's Nevyastata district slid into the excavation for a residential building.
  • On 12 November RDNSK Smolyan issued an emergency order: construction is halted and only reinforcement work is allowed.
  • Residents have contested the project for years and have filed a new appeal against the permit.
  • Off-plan buyers should expect delays and check their contract; neighbours should document every crack.

If you are thinking of buying a new-build home in Smolyan or on mountain terrain and would like a second look at the documents and the site, call us or drop by our office – we will go through together what has been checked and what is still open.

Source: BTA. This information is general and is not legal or financial advice.

Author

Nataliya Simova

Nataliya Simova

Real Estate Broker

"Every client is special and remains a friend forever."