Varna: regional governor asks court to declare a building permit in the Sea Garden void. What the case tells property buyers
On 18 November 2026 the regional governor of Varna, Mario Smarkov, filed a report with the prosecutor's office and asked the Administrative Court in Varna to declare building permit No. 203, issued in 2020, void. The permit was issued by Varna's chief architect for a plot in the Historic Core of the Sea Garden. The following morning Varna Municipality announced it was halting the issue of any further construction documents in the case.
Below: what is known as of 19 November, and what the case means for anyone buying a property in a building that is still under construction.
The timeline, according to the regional administration
- 1997 — the plot (cadastral ID 10135.1509.7, 868 sq m) is recorded as exclusive state property.
- 2011 — a deputy regional governor draws up a deed recording it as private state property (No. 7953). According to the administration, the investor relied on that deed to apply for construction.
- 2020 — Varna's chief architect issues building permit No. 203 to Specialised Rehabilitation Hospital – Varna AD: conversion of a former laundry and boiler house into a physiotherapy and rehabilitation centre, plus 416.88 sq m of underground construction.
- 2023 — the governor refers the matter to the regional development ministry; on 22 December 2023 the minister confirms the findings, and on 22 January 2024 the 2011 deed is cancelled.
- 11 October 2024 — the chief architect issues an order (No. A-57) supplementing the permit on the basis of a new design. The state, the administration says, was not notified.
- 5 November 2026 — a deputy mayor approves a route for removing construction waste from the site between 15 November and 15 December 2026.
The governor's central argument is about competence: in his view the permit for this plot should have been issued by the Minister of Regional Development and Public Works, not by the municipal chief architect.
The investor's position had not been made public as of 19 November. The court has yet to rule; until it does, these are one party's claims.
What a "void" permit means
A building permit is an administrative act. As a rule it can be appealed within 14 days of being notified (Art. 149(1) of the Administrative Procedure Code). Nullity is different: a request to declare an administrative act void can be filed with no time limit (Art. 149(5) APC).
We covered this in October, when the regional minister said he would seek to have the permit for the building at the Asparuhovo landslide declared void. Varna now has a second such case, on a different ground.
A void act has a defect so serious that the law treats it as never having been validly issued. The textbook example in Bulgarian case law is an act issued by an authority without competence — exactly the argument made in Varna. Building permits are normally issued by the municipal chief architect, but for certain categories of project the Spatial Planning Act gives that power to the regional governor or to the minister (Art. 148(2)–(3)).
One important detail: when a permit is challenged as void after the ordinary deadlines have passed, the challenge does not suspend the permit (Art. 156(6) of the Spatial Planning Act). In principle, construction can continue while the case runs. What documents the municipality issues in the meantime is a separate matter — in Varna it has already said it will stop.
Why this matters to buyers
The project in Varna is a medical facility, not housing. But the mechanism works the same way everywhere, so the lessons are general:
1. "There is a building permit" is not a guarantee. A permit that has been in force for years can still be attacked as void. If you are buying off-plan, ask not only whether a permit exists but whether it has been challenged — in court or before the national construction control directorate. More on the checks in legal checks before buying a property.
2. Check the ownership history of the land, not just the latest document. The Varna dispute starts with a 2011 deed that changed the plot's status and was later cancelled. Where the land's history includes a state or municipal ownership deed, and the plot sits in a park, on the coast or in another sensitive zone, it deserves a separate legal review.
3. Be careful with places that are not "supposed" to be built on. Parks, the Sea Garden, green belts — the risk of a dispute is higher there and public pressure stronger. Varna recently also restricted new construction in four districts pending changes to their detailed plans — see our report on Chaika, Izgrev, Asparuhovo and Pchelina.
4. If you are a neighbour, the ordinary appeal deadlines are short. How and when to object to construction next to your home is covered in our guide to detailed plans and building permits.
Nullity of an administrative act should not be confused with nullity of a contract between buyer and seller. That is a separate subject — see when a property transaction can be challenged.
What happens next
The Administrative Court in Varna now has to open the case and rule on the request. The prosecutor's office will assess the report. The municipality has asked the regional construction control directorate for information and has begun reviewing its own officials' actions. We will follow the case.
In short
Varna's regional governor wants the court to declare a 2020 building permit in the Sea Garden void, arguing it was issued by the wrong authority on state land. Nullity can be claimed at any time, and the case on its own does not suspend the permit. For buyers the takeaway is practical: check the history of the land and whether the permit has been challenged — not just whether it exists.
If you are considering buying in a building under construction and would like us to check its documents, call us or come into the office.
Case facts as reported by the Varna Regional Administration and the media as of 19 November 2026. Statutory texts checked as of November 2026. This article is for information only and is not legal advice.