Easements and rights of way in Bulgaria: what they restrict, how they arise and how to find them before you buy a plot or a house
22 October 2026

Easements and rights of way in Bulgaria: what they restrict, how they arise and how to find them before you buy a plot or a house

A path to the neighbouring plot that runs through your yard. A manhole in the garden carrying someone else's cable. A power line over the plot that nothing can be built under. All of these are easements (сервитути) — rights that another person or a utility company holds over your property.

An easement does not take away ownership. It does limit what you can do with it, and it passes with the property to every future owner. That is why it is worth finding before you pay a deposit, not at your first meeting with the architect.

What an easement is

An easement is a limited right in rem. One property (the servient one) bears a particular use or restriction for the benefit of another property (the dominant one), or for the benefit of a company that runs a network — the electricity distributor, a gas operator, the water utility.

In practice, buyers of plots and houses most often meet three kinds:

  • a right of way across someone else's land — under Art. 192 of the Spatial Planning Act (ЗУТ);
  • a right to run service connections (power, water, sewer) from the public networks across someone else's land — under Art. 193 of the same Act;
  • energy-facility easements — power lines, gas pipelines, heating mains — under Art. 64 of the Energy Act.

Right of way: how it is created

Art. 192 of the Spatial Planning Act is clear:

  • A right of way is created by a written contract with notarised signatures between the owners (para. 1).
  • If the owners do not agree and any other technical solution is clearly uneconomic, it is created by order of the mayor (para. 2). The price is set under Art. 210 of the Act and must be paid before the order is issued (para. 6).
  • A right of way may not worsen the building conditions of the burdened land, obstruct its established use or affect lawful buildings — unless the owner of the burdened land expressly agrees to that in the contract (para. 4).
  • The contract and the order are entered in the Property Register against both properties (para. 7).

Two practical consequences:

A verbal arrangement is not an easement. An old dirt track, permission given out of goodwill or a neighbour's tolerance do not create a right you can enforce against the next owner. Whether a right of way can be acquired by prescription is a disputed point in Bulgarian case law and depends on when the use began. Do not build a purchase on it.

If you are the one who needs access, the easement is an asset. Check that it is registered against the property you are buying. A regulated building plot should, as a rule, front a street under the detailed development plan — more on that in our guide to buying a plot to build a house.

Service connections across someone else's land

When a neighbouring property has no other reasonable way to connect to power, water or sewer, the connection may have to cross yours. Art. 193 of the Spatial Planning Act follows the same model: a contract with notarised signatures is the preferred route, and without agreement the right can be established administratively only where the conditions listed in the law are met.

For you as a buyer, this means a neighbour's buried cable or pipe in the garden is not necessarily a violation — but you need to know whether there is a registered contract or order, and exactly what it allows.

Power lines and gas pipelines

For energy facilities, the easement is held by the company that builds and operates the facility (Art. 64 of the Energy Act). It includes a right of passage for people and equipment and restrictions on how the land can be used within a defined strip — the easement zone. Under the general rule, the easement arises once there is a detailed development plan in force that fixes the location and size of the zone, and a one-off compensation has been paid or deposited for the owner.

For easements outside built-up areas, compensation is set by a municipal commission at market value (Art. 210 of the Spatial Planning Act), and its decision can be appealed to the administrative court within 14 days of the notice (Art. 215).

What cannot be done inside the zone of an overhead power line? Ordinance No. 16 on energy-facility easements (Art. 14(1)) prohibits buildings of any kind, perennial trees, parking vehicles and storing materials there. The operator has a right of access for repairs and maintenance and may cut branches and trees within the zone.

Indicative zone widths under Ordinance No. 16:

FacilityEasement zone
Medium-voltage overhead line, in a settlementthe conductors + 2 m on each side
110 kV overhead line, in a settlementthe conductors + 4 m on each side
220 kV overhead line, in a settlementthe conductors + 6 m on each side
400 kV overhead line, in a settlementthe conductors + 9 m on each side
Low/medium-voltage underground cable, in a built-up area1.5 m on one side and 0.6 m towards buildings
Gas transmission pipeline up to DN 100015 m on each side

For gas distribution pipes inside towns and villages the zones are much narrower — from a few tens of centimetres to a few metres, depending on the type of pipe.

If the plot is 600 sq m and a 15–20 metre strip that cannot be built on crosses it, that changes both the house design and the value of the land.

How to find an easement before you buy

  1. Property Register. Request a search on the property's file. Contracts under Arts. 192 and 193 and mayoral orders are registered there.
  2. Cadastral map and detailed plan. The cadastral extract shows linear infrastructure; the detailed plan shows easement zones and access roads. Compare both with what you see on the ground.
  3. Site visit. Poles, manholes, gas-pipeline marker posts, a worn path, a second gate to the neighbour — each is a reason to ask.
  4. Questions to the seller and the neighbours. Has compensation been received? Are there any access arrangements? Any disputes?
  5. The notarial deed. It may mention encumbrances, but it shows the position on the day of the previous sale. How to read one is covered in our guide on reading a Bulgarian notarial deed.
  6. Design visa and utility data. If you are buying to build, the design visa and the technical data from the power and water utilities show the real constraints — and you can request them before completion, with the owner's consent.

Access and utilities are a particularly common issue with holiday and village homes around Sofia — see our guide to buying a village house or holiday cottage near Sofia.

How an easement affects the deal

  • Price. A strip where you cannot build or plant trees reduces the usable area. In our experience buyers and valuers take this into account — so it is better for the seller to raise it first.
  • Design. Building lines and easement zones decide where the house can stand. Sometimes that is the difference between the house you want and the house you can build.
  • Preliminary contract. If you know about an easement, describe it. If you do not, ask the seller to declare that there are no encumbrances or arrangements other than those registered.

An easement is rarely a reason to walk away from a good property. The surprise is. If you like a plot or a house and want us to check what runs across it, under it and over it, call us or come into the office — we will go through the documents and visit the site with you.

Verified October 2026. Zone widths follow Ordinance No. 16 and are indicative — the actual zone is set by the detailed plan and the specific facility. This is general information, not legal advice for a specific case.