The last unfinished section of the Sofia Ring Road – the south-western arc between Bratya Buxton Blvd. and the Struma motorway, crossing Tsar Boris III Blvd. – has moved from planning to expropriation. On 6 October 2026, Regional Development Minister Ivan Shishkov said the full zoning plan had now been approved and that a Council of Ministers decision on expropriating the land should be ready within one to two months. For owners along the route, this is when the process becomes real.
Separately, Sofia Municipality is expropriating 21 land plots and one building for road access to the future National Children's Hospital, which links to the ring road. According to the municipality in mid-September, the procedure was complete and compensation paid for 14 of them, with amounts for the remaining 7 still to be set.
The announced timeline is indicative. Minister Shishkov expects the road to be finished in about three years – roughly one year of design and two of construction. Design is expected to start by the end of 2026, and construction mid-2027 at the earliest, depending on expropriation, public tenders and possible appeals. No project cost or secured funding has been announced so far.
The Boyana interchange, partly closed to traffic for more than two years, will be addressed within the overall project; until then the restrictions remain.
The ring road is part of the national road network, so expropriation follows the State Property Act (ZDS). The key rules:
Part of a property can also be expropriated. Then the key question is whether the remainder can still be used for its purpose – which directly affects its value.
If you own property on the route: check with Sofia Municipality or the Chief Architect's office whether it falls within the approved PUP, follow the official notices, and keep records of anything that affects value – improvements, permits, lease agreements. If you disagree with the compensation, the appeal window is short.
If you are buying in Knyazhevo, Ovcha Kupel, Gorna Banya, Suhodol or Lyulin: before signing a preliminary contract, get a cadastral sketch and check whether the property is affected by the road PUP. This is part of the standard legal due diligence before buying. A property next to the future route will be better connected, but will also live through several years of construction – both should be reflected in the price.
This is the latest major infrastructure change in the capital, following the municipal transport and boulevards programme of up to €367 million.
This article is for information only and is not a substitute for specific legal advice.