Plovdiv ring road: work on the south-eastern bypass resumes, with October 2027 as the target
On Tuesday, 8 September, Regional Development and Public Works Minister Ivan Shishkov said talks are under way with the contractor to finish Plovdiv's ring road by October 2027, while Prime Minister Rumen Radev visited the section currently under construction. Three days earlier the Plovdiv Regional Administration announced that work on the south-eastern bypass had resumed after a halt of several months. The information comes from BTA, BNT and the Plovdiv Regional Administration.
What happened
On 5 September, Plovdiv Regional Governor Georgi Yanev inspected the south-eastern bypass. Construction had been stopped for several months because of weak ground along the route. The design was reworked, and the expert council of the Road Infrastructure Agency approved the continuation of the works. The contractor is Trace Group Hold AD.
According to the contractor, on the Asenovgradsko Shose side the work is at a key stage: forming the subgrade, the first stable foundation of the future road. Placing the mineral layers and laying the asphalt come next.
On 8 September, after the opening of a factory expansion in the Trakia Economic Zone, Minister Shishkov said that "almost nothing" had been built on the site over the past two or three years and that there were many problems with both design and construction. All responsible institutions will work in parallel to meet the deadline, and the contractor has to keep to its commitments. He added that the entire Plovdiv ring road is being designed and that the project will be reworked, after which its cost will become clear.
The same day PM Radev visited the section under construction. According to BNT, the deadline for completing the works is October 2027.
The south-eastern bypass at a glance
| Item | Details |
|---|---|
| Groundbreaking | September 2024 |
| Length | about 4.5 km |
| Cross-section | G20: two lanes each way with a central reservation |
| Largest structure | overpass over the Plovdiv–Dimitrovgrad railway, 10 m high and 86 m long |
| Target date | October 2027 |
The bypass is meant to create a direct link from Asenovgradsko Shose to the Trakia motorway and towards Smolyan and the Kapitan Andreevo border crossing. It should take through traffic out of the city and shorten journeys between the motorway, Asenovgrad and Smolyan.
Alongside the road works, teams from the National Archaeological Institute with Museum at the Bulgarian Academy of Sciences are excavating an ancient settlement from the 4th–2nd century BC along nearly 700 m of the route, near Trakia railway station. The excavations began on 7 August and are expected to finish by early November at the latest.
Open issues remain: moving an EVN transformer station off the route (the design is ready, but the work is delayed) and two crossings of the southern bypass sewer collector. The regional working group is due to meet and will look at these problems specifically.
What it means for buyers and owners
Buyers of homes in the southern and eastern parts of the city. A finished bypass would ease traffic around Asenovgradsko Shose and improve access to the Trakia motorway. Today, though, it is a target, not a finished road. The project broke ground in 2024, stopped for months and is now restarting with a reworked design. It is sensible to value a home on what it offers now, such as transport, schools and parking, and to treat the future road as a possible bonus rather than a certainty.
Anyone looking at property near the route. A four-lane road nearby also means noise, and construction work over the coming months. Before buying, check the detailed development plan for the area and whether the property falls within or next to the road's easement. This is part of the wider due diligence set out in our guide to legal checks before buying.
Owners who are selling. The news is a good talking point with buyers, but it is not a reason to raise the price in advance. Buyers know the history of delays. Prices in the area will follow actual progress, not announced deadlines.
Plots and warehouse space. The announcement came on the same day a factory expansion opened in the Trakia Economic Zone. A better link between Asenovgradsko Shose and the motorway matters for logistics, but with plots you should also check the land's permitted use and its road access.
If you are looking for a home in Plovdiv, see our guide to Karshiyaka. The municipal acquisition tax in Plovdiv is 3%, and our guide to the property acquisition tax explains how it is calculated.
In short
- Work on Plovdiv's south-eastern bypass has resumed after a halt of several months caused by weak ground and a redesign.
- Minister Shishkov: talks are under way with the contractor to finish by October 2027. The whole ring road is being designed, and its cost will be known after the redesign.
- The bypass is about 4.5 km long, with an overpass over the railway. The archaeological excavations are expected to finish by early November.
- For buyers: treat the road as a possible future benefit, not a given, and check the zoning plan and easements for property near the route.
If you are thinking of buying or selling property in or around Plovdiv, call us or visit our office. We will tell you what is actually changing around the specific address.
Sources: BTA, BNT, Plovdiv Regional Administration. This information is general and is not legal or financial advice.