First stage of the Maria Luiza Boulevard tram track rebuild is complete in Sofia: 507 m with new utilities, overhead lines and lighting

First stage of the Maria Luiza Boulevard tram track rebuild is complete in Sofia: 507 m with new utilities, overhead lines and lighting

On 12 September 2026 Sofia Municipality announced that the first stage of the tram track reconstruction on Knyaginya Maria Luiza Boulevard has been completed – the 507 m section between Opalchenska Street and Hristo Botev Boulevard. Trams have already completed 72-hour test runs on the renewed section, and from 14 September they are back in service there.

What has been done

According to the municipality, on the first section:

  • the underground utilities were fully replaced;
  • the drainage system was rebuilt;
  • the overhead contact network above the track was renewed;
  • new street lighting was installed;
  • the stops were renovated and made accessible to people with reduced mobility.

The whole project covers 1.2 km of tram track, from Opalchenska Street to Kozloduy Street, and work began in early June. Mayor Vasil Terziev said he was pleased with the pace on site and that the aim had been to restore part of the public transport service before the start of the school year. Deputy Mayor for Public Construction Nikola Lyutov said the works are on schedule and the route will be renewed in stages.

Public transport changes from 14 September

With the first section open, tram service has been partly restored around the Fifth City Hospital and the 7th Diagnostic and Consultative Centre:

LineChange from 14.09.2026
Trams 12 and 27restored
Trams 3, 4, 6 and 7partly changed routes
Buses 78, 213, 305 and 404partly changed routes
Temporary bus line A3TMopened

Source: Sofia Municipality, 12.09.2026.

What comes next

The next stage covers the junction of Knyaginya Maria Luiza and Hristo Botev boulevards. It includes a full rebuild of the track and automation of the tram switches, a new overhead contact network and street lighting, and telecom ducts serving the residential area and the railway station complex.

When work began in June it was announced that the project would be carried out in five stages, with construction and renovation works worth over €8.5 million (according to the contractor, the Transpat Infra 2022 consortium). According to BTA's report at the start of the works, the whole project is expected to be completed by April 2027. The municipality has not announced a separate deadline for the next stage.

Context

Knyaginya Maria Luiza Boulevard links central Sofia with the Central Railway Station and carries one of the city's oldest tram routes. The works are part of a wider wave of infrastructure projects in the capital – at the end of August, for example, construction started on Kopenhagen Boulevard in Mladost, with a new tram line to Mladost 3 metro station.

What it means for owners, buyers and tenants

Owners on the boulevard and in the surrounding streets. New underground networks, drainage and lighting mean fewer breakdowns and a better street environment for years to come. While the works continue, though, there will be a construction site, noise and diverted transport along the route – especially around the Hristo Botev junction, where the next stage takes place. If you are selling now, tell buyers plainly what is coming and when – it avoids surprises and last-minute haggling.

Buyers. Homes close to a renewed tram route in a central area usually benefit from better access and a more pleasant street, but the benefit arrives after the works are finished, not before. Before you buy, check which stage covers the stretch in front of the building and how long it will last. If the flat faces the boulevard, look at the windows and sound insulation – the tram stays, new track or not.

Tenants. During the works, journeys may take longer because of the diverted routes. Check the current lines before signing a lease in the area.

In short

  • The first stage (507 m) of the tram track reconstruction on Knyaginya Maria Luiza Boulevard – between Opalchenska Street and Hristo Botev Boulevard – is complete.
  • Underground utilities, drainage, the overhead network and lighting were replaced; the stops are now accessible.
  • From 14 September trams 12 and 27 are back, while other lines run on partly changed routes.
  • Next is the Hristo Botev junction; the whole project runs 1.2 km to Kozloduy Street.

Own property near Maria Luiza Boulevard or looking for a home in central Sofia? Call us or visit our office – we will help you assess how the works affect the specific property.

Source: Sofia Municipality; BTA. This information is general and does not constitute legal or financial advice.

Author

Rumyana Kolarova

Rumyana Kolarova

Senior Broker

"Precision and integrity with clients and colleagues."