Buying new-build property in Bulgaria: what Act 14, Article 181, Act 15 and Act 16 actually mean

Buying new-build property in Bulgaria: what Act 14, Article 181, Act 15 and Act 16 actually mean

With new-build property, the price almost always depends on the construction stage. The earlier you commit, the better the terms — and the larger the share of the risk you, rather than the developer, are carrying.

The difficulty is that these stages are discussed in shorthand that does not match their legal meaning. "The building has Act 14" sounds like the finish line, when in fact it is not even sufficient to establish that the building has reached rough-construction stage. Here is what each stage actually means — and where it is decided whether your purchase is protected.

Stage 1: building permit — you are buying a right, not a property

Until the building is completed to rough-construction stage, what can be transferred is the right to build, not the apartment itself. This follows directly from Article 181(1) of the Spatial Development Act (ЗУТ).

In practice, off-plan purchases are structured through a preliminary contract under Article 19 of the Obligations and Contracts Act, combined with a construction agreement. A preliminary contract does not transfer ownership — it creates an obligation to conclude a final contract. If the other side refuses, the performing party may ask the court to declare the contract final under Article 19(3). That is real protection, but it is a court route: it takes time, and it assumes the contract was drafted precisely enough to be enforceable.

At this stage, therefore, the quality of the contract matters more than anything else.

Stage 2: rough construction — Act 14 is not enough

This is where the most common mistake is made.

Act 14 is the acceptance protocol for the structure under Regulation No. 3 of 31 July 2003. It is drawn up by the participants in the construction process — the structural designer, the contractor and the structural engineer acting for the construction supervisor. In other words, it is an internal document signed by the parties building the project.

The document with external legal force is a different one: the certificate of completion stage under Article 181 of ЗУТ. It is issued by the municipal administration, following an inspection on site and of the documentation, and certifies that the building meets the "rough construction" stage as defined in § 5, item 46 of the Act's supplementary provisions — enclosing walls and roof completed.

Why this matters to you:

  • From that moment on, what can be transferred is the building itself or individual units within it (Article 181(2)), rather than a right to build.
  • Banks finance a purchase against this certificate, not against Act 14.
  • The certificate is also required by the cadastre in order to enter the new building on the cadastral map.
  • Under Article 14(2) of the Local Taxes and Fees Act, the developer must declare the building to the municipal tax office within two months of completion to rough-construction stage.

If a seller tells you the building is "at rough construction", ask for the Article 181 certificate — not the act.

Stage 3: Act 15 — handover from contractor to developer

Act 15 is the protocol establishing that the works are fit for acceptance. Through it the contractor hands the building and the construction documentation over to the developer.

Two clarifications that prevent misunderstandings:

  • Act 15 is not an occupancy permit. The building has not yet been commissioned.
  • This is the stage at which objections are raised. If there are not sufficient guarantees that the building will function normally, the act should not be signed until the outstanding works are completed.

Buying after Act 15 but before Act 16 is common practice — but it carries the risk of an open-ended delay. There is no fixed deadline for commissioning, and it can be extended by another owner's refusal to sign.

Stage 4: Act 16 — the warranty clock starts here

Act 16 is the protocol establishing fitness for use, on the basis of which either an occupancy permit (for higher construction categories) or a commissioning certificate (for category IV and V buildings, issued by the municipality's chief architect) is granted.

Its practical significance is twofold: the building may lawfully be occupied, and the statutory warranty periods begin to run from commissioning — not from Act 15, and not from the notarial deed.

Warranty periods: how long the contractor remains liable

The minimum periods are set out in Article 160(3)–(5) of ЗУТ and Article 20 of Regulation No. 2 of 31 July 2003:

  • 10 years — all newly executed structural elements of buildings and facilities, including the ground beneath them;
  • 8 years — restored structures of buildings that have suffered failures;
  • 5 years — waterproofing, thermal, sound and anti-corrosion works in a non-aggressive environment (3 years in an aggressive environment);
  • 5 years — all other construction, installation and finishing works, and internal building services.

A contract may provide for longer periods, but not shorter ones than the statutory minimums.

And one point rarely explained to buyers: if you purchase from the developer as the commissioning party, you can negotiate longer periods directly. On a resale, however, you are a third party to the contract between developer and contractor and can rely only on the statutory minimum — unless the warranty rights are expressly assigned to you with the contractor's prior consent. It is worth asking about that clause before you sign.

VAT: why new construction carries 20% in the price

Under § 1, item 5 of the supplementary provisions of the VAT Act, "new buildings" are those which at the date of supply are at rough-construction stage, or for which 60 months have not elapsed since the occupancy permit or commissioning certificate was issued.

The sale of a new building by a VAT-registered person is a taxable supply carrying 20% VAT. That is why new-build asking prices are normally quoted "VAT included", whereas resales of older homes between private individuals carry no VAT at all. When comparing offers, check explicitly whether the quoted price includes the tax — the difference is not cosmetic.

The most underestimated risk: the developer's mortgage over the land

In most projects the developer finances construction with a bank loan secured by a mortgage over the plot. That mortgage encumbers the units in the building as well.

If it is not discharged — or at least partially released for your unit — before or simultaneously with the notarial transfer, you acquire a property burdened by someone else's debt. The mechanism is standard and entirely solvable: the developer's bank issues consent to a partial discharge, coordinated for the completion date. But it has to be written into the preliminary contract as an obligation with a deadline, rather than arranged on the day.

Encumbrances are checked through a certificate from the Property Register, obtained immediately before the notary — we set out the full procedure in our guide to legal checks before buying.

What belongs in the preliminary contract

For new construction the minimum is broader than on a resale:

  • Precise identification of the unit — area, floor level, neighbouring units per the design, share of common parts and of the right to build.
  • Stage and deadline — which stage the developer commits to and by when, with a clear penalty for delay.
  • Specification of the finish — exactly what "turnkey" or "plaster and screed" includes, with a materials schedule attached.
  • A payment schedule tied to construction stages — not to calendar dates.
  • The developer's mortgage — deadline and mechanism for discharge or partial release.
  • Warranty periods — confirmation of the statutory minimum, and an express assignment of rights where applicable.
  • The right to withdraw without penalty if bank financing is refused.

If you are buying with a loan, note that the bank will only release funds after the stage it recognises. For an initial estimate you can use the mortgage calculator, and we have summarised lending conditions in our mortgage guide.

What we take care of

On new-build transactions, checking the project is part of our ordinary work rather than a separate service. We verify the construction status from the documents, not from the listing description; we ask for the Article 181 certificate rather than Act 14; we trace the encumbrances over the plot and negotiate the mechanism for discharging them; and we renegotiate the preliminary contract instead of signing it as presented.

If you are considering a new-build purchase and would like the contract reviewed by a lawyer before you pay a deposit — call us or come by the office. We will go through the documents together and tell you plainly what is in order and what needs to be settled before the notary.

Author

Hristiyan Markov

Hristiyan Markov

Legal Counsel

Solving every case requires in-depth analysis and a professional attitude.